Infrastructure Advisory

Plan, source and run AI infrastructure

Independent advice on GPU capacity: what to rent or buy, where to put it and what you should be paying. From a one-off cost review to running provider selection for you.

Monthly GPU costMarket reference
Hyperscaler on-demandUS$40k
Specialist cloud on-demandUS$20k
1-year reservedUS$14k
Saving vs hyperscaler on-demandUS$26k / month65%
H100 list-price references, Sep–Oct 2026 · your quote depends on term and region
The problem

The same GPU-hour can cost several times more

The GPU market is opaque. The same H100-hour was listed in late 2026 at roughly US$6.88 on a hyperscaler, around US$3.39 on a typical specialist cloud and about US$2.44 on a one-year reserved term. Most teams are on whichever option they started with.

Prices also move. One-year H100 rates bottomed in late 2025 and climbed through 2026. Contract terms, prepayment and the provider's own financial health matter as much as the hourly rate.

  1. PriceWhat should we pay?Benchmarked against current market rates for your GPU type, term and region.
  2. TermsWhat are we signing?Minimum terms, prepayment, exit clauses and counterparty risk, reviewed before you commit.
  3. PlaceWhere should it run?Region, operator and jurisdiction matched to your data rules.
Power planner

What a GPU cluster draws from the grid

Choose a server type and a cluster size to see the power, cooling and rack space it needs.

Power is now the scarcest input in AI infrastructure. A modest cluster can need more grid capacity than an entire floor of ordinary servers, and rack densities have moved past what traditional air cooling handles. These are the first numbers we check when a client is planning a build or comparing colocation offers.

GPU server
Servers 32 × 8 GPUs = 256 GPUs
IT load326 kW
Facility · PUE 1.3424 kW
Energy per year3,717 MWh
Per rack41 kW
8 racksRear-door heat exchangers or liquid
Grid connection used (of a 2 MW hall)
21%
Vendor nameplate power, 4 servers per rack, PUE 1.3 · planning estimate, not a site survey
An engineer in a hard hat and safety vest holds rolled plans and looks up at cooling pipes in a data hall under construction
On the ground

Advice from people who walk the data halls

Spec sheets and sales decks only tell part of the story. Before we recommend a facility, we check the power actually contracted to it, the cooling the halls can take, and the lead times on the GPUs and networking you'd be waiting for.

For clients building their own capacity we work from site selection through procurement and commissioning. For those renting, we benchmark offers against the market and negotiate the terms that usually get missed: power pass-through, uptime credits, exit rights and where your data is allowed to go.

Power first
Contracted grid capacity checked before anything else
Independent
We compare suppliers, not sell one
End to end
From site selection to a running cluster
What we cover

Every layer of the infrastructure decision

01

GPU sizing

Which GPU, how many and for how long, based on your models, data and deadlines.

02

Cost reduction

Move steady workloads off on-demand pricing and right-size idle capacity.

03

Provider sourcing

Requests for quotes across specialist clouds, with a side-by-side comparison.

04

Migration planning

Move training and inference between providers without downtime or data loss.

05

AI servers on-premises

NVIDIA DGX or HGX-based AI servers specified, priced and bought through authorised distributors, with power and cooling planned.

06

Site selection

Colocation options across Singapore, Johor and Batam, with operator introductions.

Locations

AI data centre sites: Singapore, Johor or Batam?

Indicative colocation economics for AI deployments near Singapore, as of late 2026.

Item
Singapore
Johor
Batam
Colocation (per kW, per month)
Singapore~US$330–475
Johor~US$110–150
BatamLower; varies by campus
New capacity
SingaporeScarce; allocated by government call
JohorGrowing fast; AI-led builds
BatamNew campuses opening from 2027
Latency to Singapore
Singapore—
JohorA few milliseconds
BatamUnder 2 ms on new subsea cable
Data law
SingaporeSingapore PDPA
JohorMalaysia PDPA
BatamIndonesia PDP Law
Watch-outs
SingaporeCost, power limits
JohorWater and power curbs; export permits for US AI chips
BatamNewer ecosystem

Sources: CBRE, Coloprice, SubTel Forum and Malaysian MITI statements, 2026. Figures are indicative and change quickly.

Engagements

Advisory engagements

Fixed-fee reviews and sourcing projects, or an ongoing retainer. Any provider fees we receive are disclosed to you.

Launch

A GPU cost and sizing review of your current setup.

  • Spend and utilisation analysis
  • Right-sizing recommendations
  • Market price comparison
Enquire for pricingEnquire →
Most popularScale

Sourcing and migration: we run the process with providers for you.

  • Requests for quotes across providers
  • Contract and counterparty review
  • Migration plan and cut-over support
Enquire for pricingEnquire →
Fleet

Ongoing infrastructure partner for multi-region AI operations.

  • Quarterly capacity and cost reviews
  • Colocation and site selection
  • On-call engineering support
Enquire for pricingEnquire →
Eligibility

We never sign end-user or export statements on a client's behalf. You remain the buyer of record for any hardware or capacity you purchase.

How it works

From review to running capacity

  1. 01

    Review

    Your current spend, utilisation and contracts, benchmarked against the market.

  2. 02

    Recommend

    Target setup, providers and terms, with a cost model you can share internally.

  3. 03

    Source

    We run the quotes and negotiation. You sign directly with the provider.

  4. 04

    Migrate

    Cut-over plan, testing and support until the new setup is stable.

Case studies

Systems we've shipped for clients

InterContinental Phuket ResortLuxury Hospitality
Top 5

Google ranking vs. parent brand + OTAs

SEOAI Content PipelineTechnical SEOInsightAX

AI-accelerated content pipeline producing destination, itinerary and long-tail search pages at scale — ranking the resort above IHG's main page and top OTAs for core terms.

"Axccelerate's strategic approach to content and SEO significantly improved our digital visibility. Their ability to secure top search rankings alongside major travel sites established our position in the luxury Phuket market."

— InterContinental Phuket Resort
Read the full case study
FAQ

Infrastructure questions

Find out what your GPUs should cost

Send us your current setup. We'll come back with a benchmark and the options worth pursuing.